Tengiz Oilfield Recovery to Reach Less Than Half of Normal Output by February 7, Sources Say

Restart proceeds slowly after generator fire and power outage; export flow via CPC remains constrained as force majeure stands

By Sofia Navarro
Tengiz Oilfield Recovery to Reach Less Than Half of Normal Output by February 7, Sources Say

Kazakhstan’s largest oilfield, Tengiz, is restarting production following a January 18 outage caused by a generator fire, but two industry sources say recovery is likely to leave output below half of normal levels by February 7. Officials and the operator report partial restarts, while uncertainty over the pace of recovery and the continued force majeure on CPC Blend exports leave Kazakhstan’s oil shipments and national output projections under strain.

Key Points

  • Tengiz and Korolev production was halted on January 18 after a generator fire caused a power outage; exact cause of the fire is unclear.
  • Two sources estimate Tengiz will produce about 33,000 metric tons per day by February 5 (roughly 260,000 bpd or 26% of normal) and 57,000 metric tons per day by February 7 (about 46% of normal).
  • The field’s crude is mainly exported via the Caspian Pipeline Consortium (CPC), which handles about 80% of Kazakhstan’s oil exports; TCO has not lifted force majeure on CPC Blend supplies, affecting export flows.

MOSCOW, Jan 27 - Kazakhstan’s Tengiz oilfield, the country’s largest, is in the process of restoring production after a shutdown triggered by a fire at a generator and the consequent power outage, but two sources familiar with the situation told Reuters they expect output to remain below half the field’s typical level by February 7.

The outage at Tengiz - which, along with the Korolev field, had its production temporarily halted on January 18 by operator Tengizchevroil (TCO) after the generator fire - represents another disruption for Kazakhstan’s oil sector. The country has already faced limits to its main export route in recent months following an attack by Ukrainian naval drones.

It remains unclear what caused the generator fire. Chevron, the lead partner in the consortium operating Tengiz, said on Monday that oil production had been restarted, but did not specify which field that referred to. Kazakhstan’s energy ministry reported on Monday that Tengiz was preparing to resume output soon and that Korolev was already operating again. Despite these statements, TCO has not yet rescinded a force majeure declaration it issued on CPC Blend crude supplies after the shutdown.

One source who spoke on condition of anonymity because they were not authorised to speak to the media provided estimates for the near-term recovery path. The source said the fields were expected to produce 33,000 metric tons per day by February 5, which corresponds to about 260,000 barrels per day or roughly 26% of usual volumes. By February 7, that source projected daily production would rise to 57,000 metric tons - about 46% of typical levels - but emphasized that the extent of further recovery remained uncertain.

Another source described restoring Tengiz to its normal operational profile as a difficult task and said the pace of recovery was hard to estimate. "Oil output has been restarted and will reach a decent level in a week or so but it’s hard to say what’s next," the source said, adding that Tengiz would likely struggle to meet its planned export schedule.

A third source offered a different near-term view, suggesting Tengiz output could approach 670,000 barrels per day by mid-February, a level comparable to output seen in autumn but still below the roughly 900,000 barrels per day the field reached earlier last year.

Tengiz, located in western Kazakhstan, is identified by Chevron as the world’s deepest producing supergiant oilfield, and extraction there involves substantial technical challenge. The bulk of Tengiz’s crude moves to markets through the Caspian Pipeline Consortium (CPC), which transports about 80% of Kazakhstan’s oil exports. TCO’s decision to maintain force majeure on CPC Blend shipments means export flows tied to that grade remain constrained.

Financial markets and industry analysts have also weighed in on the probable national impact. JPMorgan estimated on Friday that Tengiz might remain offline through the end of the month and projected Kazakhstan’s January crude output would average between 1 million and 1.1 million barrels per day, compared with the roughly 1.8 million barrels per day the country typically produces.

At the government level, Kazakhstan said Prime Minister Olzhas Bektenov met with ExxonMobil Vice President Peter Larden on Monday and urged the U.S. energy company to accelerate work to address the outage and to take steps aimed at preventing similar incidents in future. Within the TCO consortium, Chevron holds a 50% stake, ExxonMobil owns 25%, Kazakhstan’s KazMunayGaz controls 20% and Russia’s Lukoil has 5%.

As Tengiz works through the phased restart and authorities and partners assess the condition of production infrastructure, both the timeline for a full recovery and the impact on Kazakhstan’s export schedules remain subject to significant uncertainty.

Risks

  • Recovery speed and ultimate restoration of normal Tengiz output are uncertain - this affects oil export volumes and national production statistics, impacting energy and commodity markets.
  • Continued force majeure on CPC Blend shipments keeps a major export route constrained, posing risks for logistics, trading firms and refineries reliant on Kazakh crude.
  • Technical challenges at Tengiz and the unclear cause of the generator fire imply operational risk for the field and potential for further unplanned outages, which could disrupt supply and influence market sentiment.

More from Commodities

Gold Plunge Intensifies After CME Margin Hikes and Warsh Nomination Spurs Market Reassessment Feb 2, 2026 European Gas Prices Plunge as Forecasts Turn Milder Feb 2, 2026 BCA's MacroQuant Sees Dollar Weakness; Boosts Oil, Copper and Gold Calls Feb 2, 2026 Russian Oil Transit Through Ukraine Falls to Decade Low Amid Pipeline Strikes Feb 2, 2026 Kremlin Says Russia Presses on With Efforts to Reduce Tensions Over Iran Feb 2, 2026